Roughly all year, and the temperature rule still matters more than most people assume. Sealer is a water-based product that has to cure, not dry, and in Central Florida the rain decides the date far more often than the cold does.
The specification on the drum is a surface temperature above 50F and an air temperature above 50F, rising, and holding above 50F for the whole cure. That last part is where jobs go wrong. A sunny 62 degree January afternoon that drops to 44 overnight behind a cold front does not meet it. The coat is still curing when the temperature falls, and a coat that cures cold never reaches the hardness it was meant to reach.
You do not see this on the day. It looks like a finished driveway. You see it the following year, when the coat wears through early in the traffic lanes and starts lifting at the edges.
This is the single most common reason a sealcoating job underperforms in this part of the country, and it is entirely a scheduling decision.
In the Orlando area that works out to roughly all year. The normal January night at Orlando International is just under 50 degrees on the NOAA 1991 to 2020 normals, so a cold front in midwinter can hold a job for a day or two. The rest of the year the question is rain, not temperature.
Summer cures fast but storms most afternoons. Jobs start early so the coat has hours of dry weather behind it before the clouds build, and a day with storms forecast before noon gets moved.
Winter is the drier half of the year. The only thing to watch is a front: a night forecast well into the forties means the job waits until it has passed.
If your driveway needs it and you have the choice, the drier months from about November to April have the better argument. Fewer jobs get rained off, and the coat is fully cured and the cracks filled before the summer storms start pushing water at every opening.
The practical counterweight is that plenty of other people have the same idea, so the dry months book up first. If you want one, book early.
If a letter from your association has already set the date for you, say so when you ask for a quote. A deadline in August can still be met. It means an early start and a rain date written in from the beginning, so a storm moves the job by a day rather than past the deadline.
The surface has to be dry going down and it has to stay dry while it cures. In practice that means no rain for about 24 hours beforehand and a clear window of at least 24 hours afterwards. Rain on a coat that has not cured washes it off the driveway, streaks it into the gutter, and means doing the whole job again.
Because of that, sealcoating gets rescheduled. A contractor who will not move a job off a day with rain in the forecast is telling you something about how the rest of the work will be done. If it rains on your date, the job moves, and that is the correct outcome rather than an inconvenience.
In the cooler months there is a second problem the summer does not have. Heavy dew forms overnight once the nights get cool, and dew settling on a coat that has not finished curing does much the same thing as light rain. That is why late season work starts early in the day and stops early, rather than running to the last of the daylight.
Walking on it, a few hours. Parking on it, 24 to 48 hours depending on the temperature and the humidity, and you will get a specific window at scheduling rather than a guess.
The one that catches people is turning the wheels of a parked car on a coat that is cured but still green. Power steering on a stationary car scuffs a fresh coat easily in the first week or so. Pull in straight, and roll rather than turn on the spot until it has had a few warm days.
Two things to have done before the crew arrives: cars off the driveway including anything sitting on the apron, and sprinklers near the drive switched off for the day. An irrigation zone coming on at four in the morning onto a fresh coat is the same outcome as rain.
Test the driveway once a year, at the end of the rainy season, when you can see what the summer did to it. If the tests say it needs doing, you then have the dry months to place it rather than calling round in a panic when the HOA letter arrives. Whether your driveway actually needs sealcoating walks through the tests, and what it costs in Orlando covers how the number gets put together.